Inside the Datacenter
State Guides

Every Data Center in Ohio: Operating, Under Construction, and Proposed

A running directory of every data center campus in Ohio as of October 2026: nine operating hyperscale campuses, thirteen under construction, fifteen proposals led by the 8-gigawatt PORTS-Pike campus at Piketon, ten withdrawn or rejected, and twenty-two colocation operators by metro, plus the AEP Ohio data center tariff, the sales tax exemption fight, and the 138 local moratoriums. Every row is sourced and the list is updated as projects move.

· 21 min read

The downtown Columbus, Ohio skyline on a clear summer day seen from a bridge over the Scioto River, with the LeVeque Tower's stepped spire in the center and the Rhodes State Office Tower at right
Photo: Chris F / Pexels

This page counts every data center campus Ohio has, is building, has been offered, or has turned away, as of October 15, 2026. The tally: nine operating hyperscale and wholesale campuses, thirteen under construction, fifteen live proposals, ten withdrawn, rejected, or paused, and twenty-two colocation operators across thirty operator-metro rows. The largest project in the state is also the largest in the country on paper: the PORTS-Pike Technology Campus at Piketon, where SB Energy plans 8 GW of IT load for OpenAI on the site of a Cold War uranium enrichment plant, fed by 10 GW of new gas generation. Behind it stand Meta’s 1 GW Prometheus cluster in New Albany, Cologix’s $7 billion Johnstown campus, and Amazon’s $23 billion statewide expansion. AEP Ohio told regulators in February 2026 that it had 17,861 MW of data center load under signed contract, against a system peak that has never exceeded about 10,500 MW.

The skyline above is downtown Columbus, where the Public Utilities Commission of Ohio approved the first data-center-specific tariff in the country in July 2025 and where the General Assembly spent 2026 arguing about a sales tax exemption that cost the state $1.6 billion last year. Ohio’s tariff is the model other states are copying, and we compared it with Texas and Virginia in California’s data center laws. The bill impact of PJM’s capacity auctions, which Ohio feels as sharply as any state, is covered in AI and your electric bill and PJM’s backstop auction. The Piketon campus appears in The summer of the gigawatt campus, and Oklo’s plan to build 1.2 GW of small reactors next door is in The nuclear comeback.

At a glance

Status Projects Disclosed capacity
Operating hyperscale and wholesale 9 About 1.3 GW, mostly tracker estimates
Under construction 13 About 2.3 GW where disclosed
Proposed or pending 15 About 10.1 GW where disclosed
Withdrawn, rejected, or paused 10 About 0.4 GW
Colocation and enterprise 22 operators, 30 metro rows About 94 MW disclosed critical load

Capacity is the sum of megawatts a developer, county filing, utility, or regulator has put on the record for that bucket. Ohio’s hyperscalers disclose less than most. Amazon, Google, and Meta publish acreage and dollar pledges rather than megawatts for their operating campuses, so the operating figure leans on tracker estimates and should be read as an order of magnitude. AEP Ohio’s own numbers are the better gauge of scale: its September 2026 submission to PJM projects 13,900 MW of cumulative large-load additions by 2030 and 17,116 MW at full buildout, counting only customers with a signed agreement.

Operating hyperscale campuses

Ohio’s data center industry began in New Albany, a planned suburb on the Franklin and Licking county line northeast of Columbus, where Amazon opened its first Ohio building in 2016 on farmland that the city had annexed into a 12,000-acre business park. The city counts 40 data centers opened there since 2010 and 28 more planned or under construction. Google, Meta, Microsoft, QTS, Edged, STACK, Vantage, EdgeConneX, and Cologix have all followed Amazon into the same corn and soybean fields along Beech Road and Green Chapel Road, and the campuses now run east past Johnstown into rural Licking County.

An Ohio farm in late autumn with a red barn, a brick farmhouse, and a tractor at the edge of a harvested cornfield, with transmission lines crossing the sky overhead

Photo: Keith Cassill / Pexels

Project Operator Location Size Status Latest
AWS New Albany campus Amazon Web Services New Albany, Licking/Franklin Co. 213 MW est. Operating since 2016 Jul 2026, AWS says $39.9B invested in Ohio since 2015
AWS Scioto Darby campus Amazon Web Services Hilliard, Franklin Co. 328 MW est. Operating, expanding Oct 2026, expansion under construction per trackers
AWS Beech Road campus Amazon Web Services Johnstown, Licking Co. undisclosed Operating Jun 2025, Google bought 85 acres across the road
Google New Albany Google New Albany, Licking Co. 250 MW est. Operating since about 2020 2026, Google cites $20B+ invested in Ohio since 2019
Google Lancaster Google Lancaster, Fairfield Co. 137 MW est., 2 buildings Operating; second building live Oct 2025 Sep 2026, satellite imagery shows both buildings running
Google Columbus Google Columbus (South High St), Franklin Co. 303 MW est. Operating Jun 2024, $2.3B pledge across three Ohio sites
Meta New Albany campus Meta New Albany, Licking Co. 345 acres, 2.5M+ sq ft Operating since 2020 2026, Prometheus expansion under way (see below)
Edged New Albany Edged (Endeavour) New Albany, Licking Co. 24 MW, 206,000 sq ft Operating Sep 2025, opening celebrated
STACK NAL01 STACK Infrastructure New Albany, Licking Co. 11 MW live, 60 MW campus Operating, expanding 2026, 51 MW second building marketed for 2026 to 2027

Megawatt figures marked “est.” come from the dcmap.us and datacenterindex.ai trackers, not from the operators. AWS lists its Ohio region as New Albany, Hilliard, and Dublin, but we could not find a primary source naming a Dublin building, so no Dublin row appears.

Under construction

Project Operator Location Size Status Latest
AWS Jefferson Township campus Amazon Web Services Jeffersonville, Fayette Co. 590 acres, $5B by 2030 Under construction Jan 2025, $102.4M land purchase; 2026 operations target
AWS Sidney (Project Galaxy) Amazon Data Services Sidney, Shelby Co. $3B, 75 permanent jobs Under construction since Jan 2026 Sep 2026, recall petitions and records litigation
AWS Marysville Innovation Park Amazon Web Services Marysville, Union Co. 55 acres, 500,000 sq ft Under construction 2025, 30-year 100% abatement; completion slated 2027
Meta Bowling Green (Project Accordion) Meta Middleton Township, Wood Co. 280 acres, 715,000 sq ft, $800M+ Under construction since Apr 2025 Aug 2026, township zoning board voted 4-1 against a 39-acre expansion
Meta Prometheus Meta New Albany, Licking Co. 1 GW+ supercluster Under construction Q3 2026 target for Williams’ 400 MW Socrates gas plants
Vantage OH1 Vantage Data Centers New Albany, Licking Co. 192 MW, 1.5M sq ft, 70 acres Under construction 2026, second building topped out; first opening unconfirmed
Vantage OH2 Millersport Vantage Data Centers Millersport, Fairfield Co. 350 acres, 4 buildings, $2.1B Under construction since May 2026 2026, Fairfield Energy Center gas plant pending at OPSB
QTS New Albany 1 and 2 QTS Data Centers New Albany, Licking Co. 222 MW, 93 acres, $1.5B Under construction 78 MW first phase built; energization unconfirmed
Cologix Johnstown AI campus Cologix Johnstown, Licking Co. 800 MW, 154 acres, 8 buildings, $7B Under construction Jun 2026, $1.1B first phase announced
EdgeConneX New Albany EdgeConneX New Albany Business Park, Licking Co. 1M+ sq ft across two buildings Under construction Nov 2025, OPSB approved 216 MW PowerConneX gas plant
Aligned NEO-01 Aligned Data Centers Sandusky (Perkins Township), Erie Co. 96 MW, 129 acres Under construction since May 2024 2026 delivery expected
Aligned CMH-02 Aligned Data Centers Conesville, Coshocton Co. 197 acres Under construction Initial capacity targeted mid-2026
Prologis Project Mila Prologis Trenton, Butler Co. 141 acres, 880,000 sq ft, 4 buildings Site work; vertical build pending Mar 2026, site plan approved; first building 2028

The Cologix Johnstown campus is the one to watch in this bucket. Cologix has run the Columbus carrier hotel on Scherers Court for a decade, and in June 2026 it announced a $1.1 billion first phase of an 800 MW AI campus split between Johnstown and Orange Township in Delaware County. The Tax Credit Authority approved its 10-year sales tax exemption, worth an estimated $42.3 million, on June 1, 2026, the last such award before Governor DeWine’s pause took effect.

Proposed and pending

The newest proposals have moved well beyond central Ohio. The biggest sit in the farm counties of the south and northwest: Pike County, where the federal government’s former Portsmouth Gaseous Diffusion Plant is being offered as a 10 GW campus; Adams County, where Amazon is evaluating 1,300 MW on about 1,000 acres near Manchester; Van Wert County, where QTS has taken over a 902-acre, $10 billion plan; and Allen and Scioto counties, where Google has announced campuses at Lima and Franklin Furnace. Each of these counties is mostly farmland, and each has drawn the same question from residents that the farm towns around Columbus asked two years earlier.

A farm in rural Ohio under an overcast sky, with a weathered red barn, a white farmhouse shaded by a large tree, a windmill, and a freshly cut hay field in the foreground

Photo: Clinton Weaver / Pexels

Project Operator Location Size Status Latest
PORTS-Pike Technology Campus SB Energy / SoftBank, tenant OpenAI Piketon, Pike Co. 8 GW IT (4.25 GW first), 10 GW generation Announced; ceremonial groundbreaking Mar 20, 2026 Aug 2026, 20-year OpenAI lease, Nvidia credit support, phases from 2028
AWS Butler County campus Amazon Web Services Madison and St. Clair townships, Butler Co. 601 acres, 18 buildings, $5B Proposed; annexation contested Sep 2026, townships object; county moratorium since Jun 2026
Buck Canyon Amazon Web Services (evaluating) Sprigg Township, Adams Co. 1,300 MW by 2032, about 1,000 acres Proposed; Army Corps site-work permit Aug 2026, AES Ohio load filing; 100 MW in 2028
Midwest Digital Gateway Corscale Canton, Stark Co. 312 MW, 162 acres, $2.9B Proposed; zoning review Jul 2026, Canton adopted data center zoning rules
Google Lima (Project Bosc) Google American Township, Allen Co. 200+ acres, $500M Announced Mar 2026 Jun 2026, Ohio EPA draft air permit for 115 generators pending
Google Franklin Furnace (Project Dazzler) Google Green Township, Scioto Co. 500,000 sq ft, about $1B Proposed, early Jan 2026, county approved 75% abatement
Google Harrison Road Google Johnstown, Licking Co. 85 acres, $63M land Land banked Jun 2025 purchase; no timeline
QTS Van Wert QTS Data Centers Van Wert, Van Wert Co. 500 MW, 902 acres, up to 7 buildings, $10B Approved; groundbreaking Q4 2026 May 2026, QTS took over the project; first building Q1 2029
Vantage OH3 Vantage Data Centers Oregon, Lucas Co. 168 acres, up to 8 buildings Proposed; site plan pending Jul 2026, Vantage named as end user
Smart Farms Data Center Karis Critical New Albany, Licking Co. 114 acres, 1.6M sq ft, 8 buildings Proposed; wetlands filing 2026, disclosed through Ohio EPA filing
Cologix Orange Township Cologix Orange Township, Delaware Co. Part of $1.1B first phase Announced Jun 2026 release
Marysville South New Albany Company (end user unnamed) Marysville, Union Co. 800,000 sq ft, $1B+ Tax agreement approved 5-2 Dec 2025 council vote
Bristolville 25 Bristolville 25 Developer LLC Lordstown, Trumbull Co. 133 acres, 1.65M sq ft, $3.6B Pending; village moratorium; Supreme Court case Jun 2026, developer sought a Sep 2026 start
Project Klondike J5 LLC / Shaytura LLC Piqua, Miami Co. 607 acres, $1B Approved Nov 2025 Trackers list 2031
Pixelle mill campus U.S. Paper Mill Co. Chillicothe, Ross Co. undisclosed Proposed; 60-day city moratorium Aug 2026 moratorium, expires Oct 23

Oklo’s 1.2 GW Aurora campus on 206 acres at the same Piketon site is a power plant, not a data center, so it is not a row, but it belongs in the picture. Meta signed a prepayment agreement in January 2026 to fund the first phase’s nuclear fuel, with site work in 2026, first power as early as 2030, and the full 1.2 GW by about 2034. The PORTS-Pike campus itself was announced on March 23, 2026, by the Department of Energy, AEP, and a SoftBank-led consortium, with 9.2 GW of gas generation funded by $33.3 billion in Japanese capital and $4.2 billion committed by SB Energy for AEP’s 765 kV transmission work. State Senator Shane Wilkin called it the single most significant economic development in southern Ohio’s modern history.

Withdrawn, rejected, or paused

“Pickaway County has a lot of farmland, and I think all of it is at risk.”

Sue Carter Moore, a resident of the Ashville area, said that to WSYX in December 2025, the week the village council passed an emergency moratorium on rezoning for EdgeConneX’s 680-acre campus. Ashville’s council denied the annexation in February 2026, and the project is one of ten in this bucket, a list that did not exist in Ohio eighteen months ago. Microsoft’s three Licking County sites remain the largest pause. Microsoft stopped work in April 2025, and its June 2026 economic impact document says only that three Licking County data centers will be operational by the end of 2029. An advocacy site claims construction resumed in February 2026, but no news outlet has confirmed that, so the rows stay here.

Project Operator Location Size Outcome When
Microsoft New Albany Microsoft New Albany, Licking Co. About 184 acres, $420M+ Paused after site prep; 2029 target in Jun 2026 document Apr 2025
Microsoft Heath Microsoft Heath, Licking Co. 227 acres Paused; land kept farmable Apr 2025
Microsoft Hebron Microsoft Hebron, Licking Co. 6-building plan Paused Apr 2025
Aligned Mink Street Aligned Data Centers Pataskala, Licking Co. 200 MW, 89 acres, 3 buildings Rejected by council; Aligned seeking court review; ban on Nov 3 ballot Aug 25, 2026
EdgeConneX Ashville EdgeConneX Ashville, Pickaway Co. 680 acres Annexation denied; Supreme Court case on local authority Feb 2, 2026
Slavic Village campus Lakeland Equity Group Cleveland, Cuyahoga Co. 150 MW, 35 acres, $1.6B Permit rejected; council weighing moratorium May 14, 2026
Nordson campus conversion Cervenka Development Partners Amherst, Lorain Co. 36.6 acres, about 45 MW Use variance denied Jul 2026
Grove City campus Stream Data Centers / Headwaters Grove City, Franklin Co. 310 acres, 6 halls Blocked by 12-month moratorium; Nov 3 referendum measure Jun 1, 2026
Edged Etna Township Edged Etna Township, Licking Co. undisclosed Rezoning withdrawn Oct 2026
AWS Wilmington Amazon Web Services Wilmington, Clinton Co. undisclosed Site plan tabled; reportedly stalled Jan 2026

Pataskala is the clearest case of a market turning. Aligned’s 200 MW Mink Street site plan went to the planning commission on June 3, 2026, and lost 5-2, and the city council rejected it on August 25. Brandon Galik, the council president, told NBC4 there were big concerns with the power alone. Residents gathered more than 500 signatures afterward, and a ban on data centers over 25 MW goes to Pataskala voters on November 3, 2026.

Colocation and enterprise facilities

Ohio’s retail colocation market is three metros and a long tail. Columbus has the carrier hotel on Scherers Court in Worthington, which Cologix has grown into four buildings with a fifth due in late 2026, plus Expedient’s three sites and a cluster of smaller operators in Dublin and Lewis Center. Cleveland’s market centers on the Sterling Building at 1255 Euclid Avenue, where DataBank and BlueBridge are separate tenants on separate floors, and on H5’s Cleveland Technology Center on Rockwell Avenue, the city’s carrier hotel. The photo below looks across Lake Erie toward downtown Cleveland from the west side. Cincinnati’s largest provider is CyrusOne, which began life as Cincinnati Bell’s data center arm and still runs the old Seventh Street switch complex downtown.

The downtown Cleveland skyline seen across the calm blue water of Lake Erie from a lakeside park, framed by trees, with a stone breakwater in the foreground

Photo: Steve DiMatteo / Pexels

Operator Metro Flagship address Sites Size Notes
Cologix Columbus 585 Scherers Ct, Columbus (COL3) 4 open, COL5 due late 2026 COL3 160,000 sq ft, 18+ MW; COL4 up to 33 MW Worthington carrier hotel; Lambda AI cluster since 2025; Johnstown campus listed above
Expedient Columbus 281 E Powell Rd, Lewis Center (CMH3) 3 13.4 MW, 152,799 sq ft total Pittsburgh-based; 2N UPS at all three
Csquare (Centersquare) Columbus 8180 Green Meadows Dr N, Lewis Center 1 18,704 sq ft, 1.8 MW UPS Former Savvis, CenturyLink, Cyxtera site; only Ohio location
DartPoints Columbus 565 Metro Pl S, Dublin (CMH01) 1 5,900 sq ft hall, 345 kW 11 on-site carriers
CENTRA Digital Interconnect Columbus 6300 Central College Rd, New Albany (CMH1) 2 167,000 sq ft, 16 MW critical Also the 180 E Broad St meet-me room; CMH1 opening date not stated
Racksquared Columbus 325 E Spring St, Columbus 1 undisclosed Downtown; IBM Power cloud focus
Cogent Communications Columbus 240 N 5th St, Columbus 2 10,117 sq ft combined Carrier-operated colocation
WeConnect Columbus 35 Collegeview Rd, Westerville 1 undisclosed City of Westerville municipal data center
Expedient Cleveland 15166 NEO Pkwy, Garfield Heights (CLE1) 2 4.7 MW, 66,800 sq ft total Both buildings on NEO Parkway
DataBank Cleveland 1255 Euclid Ave, Ste 200 (CLE1) 1 7,440 sq ft, 0.4 MW Sterling Building; acquired from 365 Data Centers in 2017
BlueBridge Networks Cleveland 1255 Euclid Ave, 5th floor 2 undisclosed Separate tenant from DataBank; second site in Mayfield Heights
H5 Data Centers Cleveland 1625 Rockwell Ave (Cleveland Technology Center) 1 351,000 sq ft building Carrier hotel; Ohio IX peering; bought from ByteGrid 2017
ark data centers Cleveland 7300 E Pleasant Valley Rd, Independence 1 10,000 sq ft, 1 MW Formerly Involta; Carlyle-owned; rebranded May 2024
Cogent Communications Cleveland 1621 Euclid Ave, Cleveland 2 10,804 sq ft combined Carrier-operated colocation
LightSpeed Hosting Cleveland (Medina) 387 Medina Rd, Ste 200, Medina 1 undisclosed Small hosting and colocation shop
ark data centers Akron-Canton 191 E Miller Ave, Akron 3 Akron 20,000 sq ft, 5 MW utility; Canton 5,600 sq ft Canton site is the former SecureData 365 facility
Cogent Communications Akron-Canton 120 N Broadway St, Akron 1 50,747 sq ft building Carrier-operated colocation
LightSpeed Technologies Akron-Canton 401 Market Ave N, Canton 1 undisclosed Regional carrier with data center services
FairlawnGig Akron-Canton 3300 Fairlawn Service Dr, Fairlawn 1 undisclosed Municipal fiber utility; colocation and AWS Direct Connect
CyrusOne Cincinnati 229 W 7th St, Cincinnati (CIN2) 2 campuses CIN2 143,778 sq ft, 11 MW; Lebanon 400,000 sq ft, 35 MW Former Cincinnati Bell data center arm; Lebanon campus is CIN5 and CIN7
Flexential Cincinnati 5307 Muhlhauser Rd, West Chester 1 building, 2 halls 3.8 MW, 43,551 sq ft Former Peak 10 site; specs from Flexential’s indexed page
H5 Data Centers Cincinnati 925 Dalton Ave (Cincinnati II) 2 107,000 sq ft Second site at 360 Gest St hosts AT&T, Windstream, Zayo
DartPoints Cincinnati 302 W 3rd St, Ste 400 (CVG01) 1 13,200 sq ft hall, 180 kW Former Immedion site, acquired 2021
Encore Technologies Cincinnati 11515 Grooms Rd, Blue Ash (BLU1) 2 undisclosed Local MSP; second site in Norwood
Iron Mountain Dayton 3366 S Tech Blvd, Miamisburg (OHS-1) 1 44,000 sq ft, 1.4 MW Former IO modular site, acquired 2018
DataYard Dayton 130 W Second St, Ste 250, Dayton 1 undisclosed Downtown; operating since 1995
Encore Technologies Dayton 9333 N Springboro Pike, Miamisburg (MSB1) 1 undisclosed Address from Encore’s PeeringDB record
Telesystem Toledo Toledo NOC (address not published) 1 undisclosed Formerly Buckeye Telesystem; SOC 2 Type II
Microtronix eSolutions Ottoville (Putnam Co.) 349 Wayne St, Ottoville 1 undisclosed Published retail pricing from $5 a month

Every address above was confirmed on the operator’s own website or its own PeeringDB record. Directory sites list more: a T5 building on West 150th Street in Cleveland that was sold to StratCap in 2022, CyrusOne sites in Hamilton and Mason that have dropped off CyrusOne’s own location list, a former Involta site in Youngstown that ark no longer lists, and Bitdeer’s crypto mining halls in Massillon. None of those could be verified as an operating colocation facility and none appears in the table.

Power, policy, and moratoriums

Ohio wrote the rulebook that other states are now copying. AEP Ohio filed for a data center tariff in May 2024 after reporting more than 30,000 MW of connection requests, and the PUCO approved it on July 9, 2025, over the objections of Microsoft, Amazon, Google, and Meta, who had proposed a 70 percent minimum. The tariff applies to new loads above 25 MW and requires customers to pay for 85 percent of their subscribed capacity every month whether they use it or not, for up to 12 years with a four-year ramp, plus an exit fee equal to three years of minimum payments and collateral of half the minimum charges. The commission’s stated goal was to make developers stop reserving capacity they would never use, and by that measure it worked. After the tariff took effect, developers had 45 days to submit load studies and filed 13,022 MW across 36 sites, less than half the earlier queue. By February 2026, AEP Ohio said 5,642 MW had signed service agreements under the new tariff, on top of 12,219 MW signed before it, for a total of 17,861 MW. PUCO Chair Jenifer French told the House Select Committee on Data Centers in May 2026 that 5,642 MW is still a lot of load but a lot less than 30,000, and that the tariff had saved other ratepayers millions in unnecessary infrastructure. The Ohio Manufacturers’ Association appealed the order to the Ohio Supreme Court in November 2025, calling it discriminatory, and the case was still pending as of this writing. PUCO has since directed FirstEnergy’s three Ohio utilities to propose their own data center tariff, and AES Ohio’s pending rate case would create a separate data center class in Dayton from January 2027.

A modern white arch bridge spanning the muddy Scioto River in downtown Columbus, Ohio, with glass and brick office towers behind it and a mown lawn in the foreground

Photo: Chris F / Pexels

The second fight is over the sales tax. Ohio exempts data center equipment from sales and use tax through a program the Department of Taxation now says cost $1.57 billion in 2025, eleven times the state’s own earlier estimate. The General Assembly repealed the exemption for new projects in the 2025 budget, Governor DeWine vetoed the repeal on June 30, 2025, and House Speaker Matt Huffman spent the spring of 2026 trying and failing to find the votes for an override after Google, Microsoft, Amazon, Meta, the Ohio Chamber, and the building trades unions all wrote asking him not to. On May 27, 2026, DeWine paused all new exemption awards himself while the new Select Committee on Data Centers studies the program. Eighteen companies hold exemptions worth at least $2.3 billion in committed value, with Google, Meta, and Amazon affiliates at about $600 million each on terms that run as late as 2058. Two broader bills are stalled in the General Assembly. HB 646 passed the House 97-0 in March 2026 as a study commission and came back from the Senate as a fifty-page rewrite that would halve the exemption, cap property tax abatements, require any data center over 250 MW to bring its own power, and order PUCO to create a statewide data center rate class. Neither chamber had the votes before the summer recess. HB 706 would write the AEP tariff into state law for every utility. Maureen Willis, the Ohio Consumers’ Counsel, told the select committee in May that residential consumers should not provide free reliability insurance for extraordinary private development.

Power for the new campuses is increasingly coming from behind the meter, which House Bill 15 made easier when it took effect in August 2025. The Ohio Power Siting Board has approved five gas plants in New Albany alone: Williams’ two 200 MW Socrates plants for Meta, a 250 MW third plant with a 116 MW battery, and EdgeConneX’s 120 MW and 216 MW PowerConneX plants. Pending before the board are an 800 MW EdgeConneX plant in Pickaway County and a 1,300 MW gas plant with 1,000 MW of batteries at Millersport for Vantage. French said that in 2025 the board authorized or received applications for more than 2,000 MW of behind-the-meter dispatchable generation. Meta also signed 20-year contracts with Vistra in January 2026 for 2,609 MW from the Davis-Besse and Perry nuclear plants, including 433 MW of uprates, and in November 2025 asked PUCO to let it draw up to 250 MW from the Green Chapel substation that AEP built for Intel’s delayed fab. The bills for all of this run through PJM. Its 2027/28 capacity auction cleared at the $333.44 per megawatt-day cap, with a 5,250 MW load increase that PJM said was almost entirely driven by data centers, and Ohio’s industrial electricity prices were up 26 percent year over year in December 2025.

The local response has been the fastest in the country. The Ohio Capital Journal counted 138 municipalities and townships with active data center moratoriums as of September 17, 2026, up from about 18 in February, and 23 communities that had effectively banned the industry. Jerome Township in Union County went first in September 2025. Lordstown, Ashville, Sunbury, Jackson Township, Pierce Township, Ravenna Township, Muhlenberg Township, and two townships in Adams County followed, and Cleveland rejected a hyperscale permit in Slavic Village in May 2026. A Bowling Green State University poll in September 2026 found 78 percent of Ohioans supported moratoriums and 75 percent opposed a data center in their own community. Data centers are on the November 3, 2026, ballot in Pataskala and Grove City among other communities, and both candidates in the state’s Senate race ran on who should pay for the grid. Governor DeWine, who has defended the industry, put it plainly in June: they have to pay their own way.

How this list is maintained

Rows come from operator announcements, county and township filings, Ohio Power Siting Board and PUCO dockets, the PeeringDB facility registry, and local reporting; every row traces to at least one source in the list above, and every colocation address was checked against the operator’s own site before publication. A hyperscale or wholesale campus is one row per campus, while colocation is one row per operator per metro because Columbus is large enough that per-building rows would run to pages. Tracker estimates are marked as such. Corrections and additions are welcome through the About page, and every refresh is marked with an updated date at the top of the page.

ohiostate-guidecolumbusnew-albanylicking-countyaep-ohiopucoawsgooglemetamicrosoftpiketonmoratorium