Every Data Center in Texas: Operating, Under Construction, and Proposed

A running directory of every data center campus in Texas as of September 2026: nineteen operating hyperscale and wholesale campuses, twenty-two under construction from Abilene to El Paso, thirty-five proposals, thirteen withdrawn or rejected, and forty colocation operators by metro, plus the governor's audit that has frozen new grid connections since August. Every row is sourced and the list is updated as projects move.

· 25 min read

Aerial view of a wind farm near Groom in Carson County, Texas, with white turbines standing in green crop fields that stretch flat to the horizon under scattered clouds
Photo: K / Pexels

This page counts every data center campus Texas has, is building, has been offered, or has turned away, as of September 22, 2026. The tally: nineteen operating hyperscale and wholesale campuses, twenty-two under construction, thirty-five live proposals, thirteen withdrawn, rejected, or stalled, and forty colocation and enterprise operators by metro from the Infomart in Dallas to the border carrier hotels in McAllen and Laredo. The Texas Tribune’s own database identifies 596 operating and planned data centers statewide, and ERCOT, the grid operator for most of the state, has received interconnection requests for roughly 474 gigawatts of large load, about 90 percent of it data centers and more than five times the record demand the grid has ever served. Only 9,042 MW of that has been approved to energize.

The wind farm above stands in Carson County, northeast of Amarillo, where Fermi America is grading 6,000 acres for a campus it says will reach 11 gigawatts and where the first three gas turbines arrived by truck on September 18. Whether Fermi and the dozens of gigawatt-scale campuses behind it get grid connections is now up to the state: on August 3 Governor Abbott ordered ERCOT to audit every large project in its queue before approving another, and on September 21 he told the environmental agency to stop issuing data center permits until the audits are done. The new Texas template of a single tenant, a private gas plant, and a West Texas ranch is examined in our reporting on the summer of the gigawatt campus and on behind-the-meter power; this page is the ledger, and every row traces to a source listed at the end.

At a glance

Status Projects Disclosed capacity
Operating hyperscale and wholesale 19 About 4.7 GW, mixing live and build-out figures
Under construction 22 About 25 GW, including generation and master-plan figures
Proposed or pending 35 About 50 GW where disclosed
Withdrawn, rejected, or stalled 13 About 4 GW
Colocation and enterprise 40 operators by metro About 600 MW operating; 800 MW planned

Capacity is the sum of megawatts a developer, utility, county, or regulator has put on the record for that bucket; Texas developers quote generation capacity and master-plan totals more often than IT load, and the rows say which. For scale, ERCOT has observed a simultaneous peak of about 3.9 GW from the large loads it has approved, CBRE puts Dallas-Fort Worth’s colocation inventory at 1,432.8 MW with more than 765 MW under construction and 95 percent of it preleased, and JLL counted 6.5 GW under construction statewide at the end of 2025, more than any other market in the world.

Operating hyperscale campuses

Project Operator Location Size Status Latest
Stargate Abilene (phase one) Crusoe for Oracle and OpenAI Abilene, Taylor Co. 1,200 MW planned; about 300 MW live; 4 of 8 buildings Operating, expanding Apr 2026, completion due late 2026
Temple Data Center Meta Temple, Bell Co. 760,000 sq ft; $1.2B Operating Jul 2026, went live
Fort Worth Data Center Meta Fort Worth, Tarrant Co. 170 acres; 2.5M sq ft Operating since 2017 Jul 2026, city inventory
Midlothian campus Google Midlothian, Ellis Co. 4 buildings; fifth filed at $880M Operating, expanding Sep 2026, part of $40B Texas plan
Red Oak campus Google Red Oak, Ellis Co. First building live late 2025 Operating Sep 2026, expansion under $40B plan
Westover Hills campuses Microsoft San Antonio, Bexar Co. Multiple buildings; 245,000 sq ft addition Partly operating, expanding 2026, tracker status
FTW1 QTS Fort Worth, Tarrant Co. 52 acres; 70 MW+; 200 MW potential Operating; phase two finishing Jul 2026
DFW2 QTS Irving, Dallas Co. 56 acres; 165 MW Operating; third building opened 2025 2026
Red Oak campus Compass Datacenters Red Oak, Ellis Co. 155 acres; 9 buildings; 262 MW Operating Jun 2026, $12.6M training facility gift
Red Oak campus (DFW9 to DFW12) DataBank Red Oak, Ellis Co. 292 acres; 240 MW phase one Operating, phased 2026, phase two to 480 MW
PowerCampus Austin Skybox Datacenters Hutto, Williamson Co. 1.28M sq ft; 600 MW at build-out 2 buildings live; 2 planned 2026
The Rock Switch Round Rock, Williamson Co. 185 MW Partly operating 2026, tracker status
SDC Austin Sabey Data Centers Round Rock, Williamson Co. 84 MW; Building B adds 54 MW Operating, expanding 2026, hosts UT Horizon supercomputer
San Antonio III to VII Stream Data Centers San Antonio, Bexar Co. 1.5M sq ft; 200 MW Partly operating 2026, tracker status
Austin campus CyrusOne Austin, Travis Co. 100 MW Partly operating 2026, tracker status
Denton campus CoreWeave (former Core Scientific) Denton, Denton Co. 262 MW IT; 282 MW by 2027 Operating; 7 buildings live Jul 2026, eighth building fit-out
Helios Galaxy Digital (tenant CoreWeave) Afton, Dickens Co. 2,200 acres; 133 MW live; 1.63 GW approved Phase one operating Jul 2026, phase two due 2027
Rockdale campus Riot Platforms Rockdale, Milam Co. 700 MW; 191 MW AI lease worth $9.1B Operating; converting to AI Aug 2026, 20-year lease signed
Corsicana campus Riot Platforms Corsicana, Navarro Co. 858 acres; 400 MW built; 1 GW site Operating; AI lease talks Q1 2026

Two kinds of campus share this table. The Dallas-Fort Worth and Austin rows are conventional wholesale campuses leased to hyperscalers, clustered in Ellis County south of Dallas and along Interstate 35 in Williamson County. The rest are the new Texas model: Stargate Abilene, the first OpenAI site, has four of eight buildings running on Crusoe’s behind-the-meter gas turbines; Galaxy’s Helios in Dickens County and Riot’s Rockdale and Corsicana sites are bitcoin mines being rewired for AI tenants, and Riot’s 191-megawatt lease with an unnamed frontier lab is worth $9.1 billion over twenty years.

Under construction

Project Operator Location Size Status Latest
Stargate Milam SB Energy for OpenAI Burlington, Milam Co. 1,200 MW Under construction Apr 2026, first building due Oct 2026
Frontier Vantage Data Centers for Oracle and OpenAI Shackelford Co., near Abilene 1,200 acres; 3.7M sq ft; 1.4 GW; $25B Under construction 2026, first building late 2026
Abilene phase two Crusoe Abilene, Taylor Co. 900 MW on Lancium land Under construction; tenant unresolved Jul 2026
El Paso campus Meta and BlackRock El Paso, El Paso Co. 1 GW; $10B+ Meta share Under construction; 2,300 workers on site Jul 2026, BlackRock takes 80%; online 2028
GW Ranch Amazon (from Pacifico Energy) Pecos Co., 17 miles north of Fort Stockton 8,400 acres; 7.65 GW gas; about $12B Under construction; 3 buildings permitted Aug 2026, first power due Dec 2026
Sweetwater 1 and 2 IREN Sweetwater, Nolan Co. 2,200 acres; 2,000 MW Under construction; substation energized May 2026, 1.4 GW substation live
Barber Lake Cipher Mining (tenants Fluidstack, AWS) Colorado City, Mitchell Co. 300 MW; AWS lease $5.5B over 15 years Under construction; delivery 2026 2026, fully leased
Goodnight campus Crusoe Claude, Armstrong Co. 7 buildings; 1 GW+; $29B+ Under construction, phased to Feb 2027 Jul 2026, buildings 3 and 4 filed
Meitner Energy Center Google and Intersect Gray and Roberts Cos., near Pampa 1 GW+ with co-located wind, solar, storage, gas Under construction Jun 2026, construction launched
Wilbarger County campus Google Vernon area, Wilbarger Co. Part of $40B Texas plan Under construction Feb 2026, Google confirms build
Project Caprock (LBB-01) Aligned Data Centers Abernathy, Hale Co. 313 acres; 1.65M sq ft; 540 MW Under construction Apr 2026 groundbreaking; first delivery 2027
SAT82 Microsoft Castroville, Medina Co. 195,000 to 245,000 sq ft; up to $483M Construction from Aug 2026 Sep 2026, registered; done 2028
Bosque County campus CyrusOne Near Lake Whitney, Bosque Co. 400 MW; $1.2B Under construction 2026
CloudBurst campus CloudBurst San Marcos area, Hays Co. 1,200 MW in three 400 MW phases Under construction, first phase 2026
Edged Energy Campus Edged Martindale, Caldwell Co. 462 MW Under construction 2026
Austin campus Prime Data Centers Maxwell, Caldwell Co. 384 MW Under construction 2026
Old Settlers campus Skybox Datacenters Round Rock, Williamson Co. About 30 acres; 75 MW; no incentives Rezoned; under construction Feb 2026, council approved unanimously
TX12 Vantage Data Centers San Antonio, Bexar Co. 96 MW Under construction 2026
Georgetown campus Blueprint Data Centers Georgetown, Williamson Co. 25 MW; $160M Under construction 2026
Beacon Point Hut 8 Corpus Christi, Nueces Co. 525 acres; 1 GW site; 352 MW leased Phased construction; energization 2027 Jul 2026, phase two leased
Data Center Technology Park Tract Uhland, Caldwell Co. 2,973 acres; 4 GW plan; 360 MW phase one Permitted; early works Jan 2026, first 250 MW due 2028
TerraSite-TX1 EdgeCloudLink Houston, Harris Co. 1,000 MW hydrogen-powered per tracker Under construction per tracker 2026

The largest project on the list is not a data center but a power plant. GW Ranch, on 8,400 acres of Pecos County ranchland, is being built to generate 7.65 gigawatts of gas-fired power for Amazon, which disclosed its ownership in August and expects first power in December 2026. Meta’s El Paso campus, sold 80 percent to BlackRock in July, is the one gigawatt-class site under construction outside ERCOT, on El Paso Electric’s grid. In the Panhandle, Crusoe’s Goodnight campus at Claude and Google’s Meitner complex near Pampa are both being built with their own generation, and IREN’s Sweetwater substation, energized in May at 1.4 gigawatts, is the single largest grid connection any Texas data center has completed.

Proposed and pending

The high desert between Fort Stockton and Alpine, grassland running to the Glass Mountains and the Davis Mountains, is where the next round of gigawatt proposals is landing. Microsoft announced a two-gigawatt behind-the-meter campus at Pecos in June, and Pacifico Energy, the developer that sold GW Ranch to Amazon, approached Brewster County commissioners on September 18 about 8,400 more acres northwest of Alpine, drawing a warning from the county judge that “we’re not taking this like a lay down.”

Open grassland and low mesas near Valentine in far West Texas at sunset, with golden grass in the foreground and a wide sky of thin clouds

Photo: Tom Fournier / Pexels

Project Operator Location Size Status Latest
Pecos AI campus Microsoft Pecos, Reeves Co. 2 GW; behind-the-meter gas Announced; 5 to 7 year build Jun 2026
Project Matador Fermi America Carson Co., northeast of Amarillo About 6,000 acres; 11 GW planned; 222 MW lease worth $6.5B Site work; first turbines delivered Sep 2026, TensorWave lease delivery 2027
Data City, Texas Energy Abundance Development Laredo area, Webb Co. 50,000 acres; 5 GW; 300 MW first phase Proposed; islanded from ERCOT Feb 2026
Comanche Circle Sailfish Investors Tolar, Hood Co. 2,600 acres; up to 5 GW; 9 campuses Concept plan approved 3 to 1; hearing Oct 13 Jun 2026
Project Patriot Bilateral Energy per tracker Granbury, Hood Co. 1,200 MW Tax waiver approved 3 to 1; annexed Jun 2026
Caldwell campus PowerHouse Data Centers Uhland, Caldwell Co. 700 MW per tracker Application filed 2026
San Marcos campus Sabey Data Centers San Marcos, Hays Co. Not disclosed Application filed 2026
COPT Potranco Amazon Web Services San Antonio, Bexar Co. 600 MW Application filed 2026
SAT campus CloudHQ San Antonio, Bexar Co. 600 MW Government review 2026
Bitter Blue (Building B) Amazon Web Services Elmendorf, Bexar Co. Not disclosed Government review 2026
Palomino Alpha Palomino Zorn, Guadalupe Co. 360 MW Application filed 2026
Williamson County hyperscale campus Iron Mountain Hutto or Taylor, Williamson Co. About 500 acres; 7 buildings Application filed 2026
Project Comal KDC Real Estate Taylor, Williamson Co. 6 data centers beside Samsung Permitted 2026
Taylor campus Blueprint Data Centers Taylor, Williamson Co. 53 acres; 60 MW; $1B Approved Jul 2025; not started 2026
Jarrell campus Mesones Jarrell, Williamson Co. Not disclosed; on-site gas Incentive talks 2026
Somervell County campus Amazon Glen Rose, Somervell Co. 600 MW Tax abatement in place May 2026
C1 Jack I CyrusOne Jack Co., at the Wise Co. line 300 acres; 144 MW+; up to $2B Abatement pending Feb 2026
Waco Data Center Park InfraKey DC Parks Lacy Lakeview, McLennan Co. 520 acres; 925 MW; 1.2 GW gas plant; $10B Proposed; organized opposition 2026
RCM Hill RCM Hill LLC Hillsboro area, Hill Co. 800+ acres; 1,235 MW Proposed; sued county for $100M Jun 2026, moratorium rescinded
Hubbard campus Nexus Data Centers Hubbard, Hill Co. 5,630 MW per tracker Planned 2026
Project Merlin Galaxy Digital McGregor, McLennan Co. 3,500 MW per tracker Planned 2026
East Texas campus Amp Z Lufkin, Angelina Co. 2.1 GW; 175 MW grid in 2026 Land deal; planned 2026
RGV Data Center Project Eneus Energy Harlingen, Cameron Co. 2,000 MW; 4.6M gallons a day reclaimed water Proposed 2026
Childress campus Crusoe and Lancium Childress, Childress Co. 270 acres; 1 GW Announced; construction start targeted late 2026 Jul 2026
Port of Victoria campus Crusoe (power from Blue Energy) Victoria, Victoria Co. 1,600 acres; 1.5 GW; gas 2028, nuclear 2031 Planned 2026
Armstrong County campus Google Armstrong Co. Part of $40B Texas plan Announced Nov 2025
Haskell County campuses Google and Intersect Haskell Co. 640 MW solar plus 1.3 GWh storage paired Announced Jun 2026
Fort Worth campus CyrusOne and Eolian Fort Worth, Tarrant Co. 200 MW Announced Jul 2026
ACS campus ACS Fort Worth, Tarrant Co. 107 acres; 5 buildings; private substation Proposed Jul 2026
Medina County campus (SAT14A) CyrusOne West of Castroville, Medina Co. 244 acres; 500,000 sq ft first building; $4B to $6B 80% abatement; construction Dec 2026 2026
SAT93 Microsoft Medina Co. About 245,000 sq ft Registered for future construction Sep 2026
Glass Mountains site Pacifico Energy Northwest of Alpine, Brewster Co. 8,400 acres; $5B to $60B Feasibility surveys Sep 2026, pitched to county
Bastrop County land Amazon Near Cedar Creek, Bastrop Co. 1,300 acres Land acquired May 2026
Project Eagle Amazon Data Services Boling, Wharton Co. 10+ buildings of 189,060 sq ft; about $3B Registered with state Sep 2026
Floyd County data center Amazon Data Services Floydada, Floyd Co. 189,060 sq ft; $300M Registered with state Sep 2026

Three patterns. The Panhandle and West Texas rows quote generation, not IT load: Fermi’s 11 gigawatts is a gas and nuclear plant with data halls attached, and Energy Abundance’s five-gigawatt Data City near Laredo would not connect to ERCOT at all. Hood County, southwest of Fort Worth, has eight proposals on 2,600 acres and a commissioners court that approved Sailfish’s Comanche Circle without conditions in June after rejecting a moratorium in February. And Amazon has registered three new Texas projects with the state licensing agency since May without announcing any of them.

Withdrawn, rejected, or paused

Project Operator Location Size Outcome When
Stargate Abilene expansion to 2 GW Oracle and OpenAI Abilene, Taylor Co. 800 MW addition Abandoned over financing and demand Mar 2026
Project Horizon Poolside (anchor CoreWeave) Fort Stockton, Pecos Co. 568 acres; 2 GW; 250 MW first phase Anchor lease collapsed; no tenant Apr 2026
Project Matador anchor tenant Fermi America Carson Co. $150M construction funding deal Tenant withdrew; shares fell 34%; class action filed Dec 2025
Cedar Creek Reservoir campus Diode Ventures Henderson Co. 12-year build; 5M gallons a day by year five Withdrawn, citing state standards and opposition Jul 2026
Highlander SM One Highlander SM One LLC San Marcos, Hays Co. 200 acres; 380 MW; $1.5B Rezoning denied 5 to 2 Feb 2026
All data centers, city of San Marcos City of San Marcos San Marcos, Hays Co. Citywide First Texas city to ban data centers, 4 to 3 Jun 2026
Fort Spunky Pacifico Energy Hood Co., across the Brazos from Pecan Plantation 862 acres; 100 MW Concept plan revoked after water denial 2026
Project Red and Project Yellow Not disclosed Hood Co., near power plants 677 acres combined Votes delayed; under lawsuit Jun 2026
Brazoria County data center and gas plant Not disclosed Brazoria Co. 620 MW County denied tax abatement Mar 2026
College Station land sale Not disclosed College Station, Brazos Co. Not disclosed City rejected property sale after resident pressure 2026
Fort Worth campus Edged Fort Worth, Tarrant Co. Not disclosed Withdrawn; tax agreement rescinded Mar 2026
Fort Worth campus Black Mountain Fort Worth, Tarrant Co. Not disclosed Stalled after zoning approval Apr 2026
Hutto campus Zydeco Hutto, Williamson Co. 70 MW Withdrawn 2026

The Texas list of failures is mostly about tenants, not votes. OpenAI and Oracle dropped the second gigawatt at Abilene in March; Poolside’s two-gigawatt Project Horizon in Fort Stockton lost CoreWeave as its anchor in April and has not found a replacement; Fermi’s first tenant walked away in December and the company’s shares fell by a third before it signed TensorWave in August. The exceptions are San Marcos, which in June became the first Texas city to remove data centers from every zoning district, and Hill County, whose one-year moratorium lasted twenty-four days before a developer’s $100 million lawsuit forced its repeal.

Colocation and enterprise facilities

Downtown Dallas holds the two buildings that made the region a market: the Infomart on Stemmons Freeway, the 1.58-million-square-foot former computer mart that Equinix bought for $800 million in 2018 and that now houses four of its nine Dallas sites plus Cologix and DataBank suites, and Digital Realty’s carrier hotel at 2323 Bryan Street, landlord to Equinix, Rackspace, and LOGIX. Equinix’s next campus, the $836 million DA12 in West Dallas, began construction in February 2026.

Aerial view of downtown Dallas under a clear blue sky, with Bank of America Plaza, Fountain Place, and Reunion Tower rising above lower office blocks and a construction crane

Photo: Anat Morad / Pexels

Because Texas has hundreds of colocation buildings, this table lists one row per operator per metro rather than one per building. Every row was checked against the operator’s own site, an operator-maintained PeeringDB record, or a news report, not a directory listing alone; directory entries for Flexential’s downtown Austin site, Cogent, Lumen’s former Level 3 rooms, Consolidated Communications, Aptum in San Antonio, 11:11 Systems, and the state’s two Texas Private Cloud data centers were left out until an address can be confirmed. Familiar names have changed: Cyxtera and Evoque are now Csquare (formerly Centersquare, headquartered in Coppell and public since July 2026), INAP’s Plano business is HorizonIQ, ViaWest and Peak 10 are Flexential, Data Foundry is Switch, Sungard AS is 365 Data Centers in Richardson, OnRamp is Lightedge, and Alpheus is LOGIX.

Operator Metro Flagship address Sites Size Notes
Equinix Dallas-Fort Worth 1950 N. Stemmons Fwy., Dallas (Infomart) 9 operating; DA12 under construction Infomart 1.58M sq ft; DA12 372,000+ sq ft, $836M DA4 at 2323 Bryan; DA7 Plano; DA9 Irving; DA10 Richardson
Digital Realty Dallas-Fort Worth 2323 Bryan St., Dallas 12 buildings About 2.68M sq ft Carrier hotel 387,500 sq ft; 7 Richardson buildings; Lewisville 831,500 sq ft
DataBank Dallas-Fort Worth 400 S. Akard St., Dallas 8 operating; 4 Red Oak building 1.27M sq ft; about 70 MW operating; 310 MW with Red Oak DFW5 in Infomart; DFW8 Plano 40 MW
Flexential Dallas-Fort Worth 3500 E. Plano Pkwy., Plano 3 Plano about 156,000 sq ft Opened 2016 as ViaWest; Richardson and Infomart suites
Csquare Dallas-Fort Worth 14901 FAA Blvd., Fort Worth 3 238,000 sq ft; 78.8 MW utility Former Savvis, Cyxtera, AT&T, Evoque; Allen and Dallas sites
Cologix Dallas-Fort Worth 1950 N. Stemmons Fwy., Dallas 3, all in Infomart 53,000+ sq ft DAL1 is the Infomart meet-me room; 30+ cloud on-ramps
Evocative Dallas-Fort Worth 1221 Coit Rd., Plano 2 plus a point of presence DAL6 111,000 sq ft, 12 MW; DAL1 300,000 sq ft, 30 MW DAL6 former INAP; DAL1 is space inside Aligned DFW-01
TierPoint Dallas-Fort Worth 3004 Irving Blvd., Dallas 3 305,000+ sq ft; Fort Worth 5 to 18 MW Dallas former Colo4; Fort Worth bought Jan 2024
365 Data Centers Dallas-Fort Worth 1001 E. Campbell Rd., Richardson 1 75,100 sq ft; 6.2 MW Former Sungard AS; 13 carriers
Rackspace Dallas-Fort Worth 801 Industrial Blvd., Grapevine 2 DFW3 58,000 sq ft raised; 28 MW utility DFW3 inside Digital Realty Richardson; no San Antonio data center listed
CoreSpace Dallas-Fort Worth 7505 John W. Carpenter Fwy., Dallas 1 30,000 sq ft Retail colocation and hosting
TRG Datacenters Dallas-Fort Worth 4404 S. Beltwood Pkwy., Farmers Branch 1 under construction 160,000 sq ft; 25 MW First hall 2027
LOGIX Fiber Networks Dallas-Fort Worth 2323 Bryan St., Dallas 1 suite Not disclosed Carrier-run colocation inside Digital Realty
Lightedge Dallas-Fort Worth 2501 S. SH 121 Business, Lewisville 1 suite Not disclosed On the CyrusOne Lewisville campus; former Connectria
Switch (Data Foundry) Austin 4100 Smith School Rd. 2 on 40-acre campus plus legacy site DF01 130,000 sq ft, 24 MW; DF02 325,000 sq ft, 36 MW plan Texas 1 opened 2011; Switch bought Data Foundry 2021
Digital Realty Austin 7500 Metro Center Dr. 1 (AUS1) 85,500 sq ft Cloud on-ramps
Element Critical Austin 8025 N. IH-35 1 62,300 sq ft; 9.5 MW Former vXchnge
DataBank Austin 7218 McNeil Dr. 1 (AUS1) 7,870 sq ft; 0.4 MW Former Core NAP and zColo
Lightedge Austin 2916 Montopolis Dr. 2 Not disclosed Former OnRamp Access
LOGIX Fiber Networks Austin 1905 E. 6th St. 1 Not disclosed Former Alpheus
H5 Data Centers San Antonio 100 Taylor St. 2 buildings 85,000 sq ft Downtown carrier hotel; 35 carriers; SAT-IX
DataBank Houston 5150 Westway Park Blvd. 4 296,000 sq ft; 36.4 MW HOU1 15.6 MW; HOU5 in the Galleria
Netrality Houston 1301 Fannin St. 1 1.2M sq ft building; 26 MW Houston’s primary carrier hotel; 40+ carriers
Switch (Data Foundry) Houston 660 Greens Pkwy. 1 plus legacy point of presence 350,000 sq ft; 60 MW Greenspoint; 175,000 sq ft raised floor
Element Critical Houston (Katy) 22000 Franz Rd., Katy HOU1 operating; HOU2 under construction HOU1 118,000 sq ft, 40 MW; HOU2 150,000 sq ft, 60 MW 30-acre campus; 300 MVA substation
Digital Realty Houston 12001 North Fwy. 1 (IAH10) 205,500 sq ft Directories still list Level 3 here
Equinix Houston 1515 Aldine Meadows Rd. 1 (HO1) Not disclosed Former Verizon; built 1999, acquired 2017
TRG Datacenters Houston (Spring) 2626 Spring Cypress Rd., Spring HOU1 operating; HOU2 and HOU3 building 155,000 sq ft; 30 MW campus Expansion phase one late 2026
Fibertown Houston 12031 North Fwy. 1 Not disclosed Sister site in Bryan
LOGIX Fiber Networks Houston 811 Louisiana St. 2 Not disclosed Katy suite inside EdgeConneX
EdgeConneX Houston (Katy) 1510 Primewest Pkwy., Katy 1 91,400 sq ft; 17,700 sq ft raised floor Edge data center; LOGIX is a tenant
Data Journey (former Westland Bunker) Houston (Montgomery) 552 Club Dr., Montgomery 1 campus 400 MW+ planned Former Houston Bunker; 1.1 GW Sealy site proposed
DataBank Waco 700 Austin Ave. 1 (ACT1) 14,210 sq ft; 0.8 MW 12 carriers
Fibertown Bryan 110 N. Main St., Bryan 1 Not disclosed Locally owned
Crosspoint Data College Station 3001 Earl Rudder Fwy. S. 1 Not disclosed Colocation and recovery office space
MDC Data Centers El Paso 11455 Cedar Oak Dr. 1 Not disclosed First carrier-neutral site in El Paso; Mexican carrier hub
MDC Data Centers Laredo 13619 Cabezut Dr. 1 Not disclosed Two fiber crossings to Nuevo Laredo
MDC Data Centers McAllen 422 S. 11th St. 2 (MCA1, MCA2) Not disclosed Company headquarters; 62 networks across 9 border markets
1547 Critical Systems Realty McAllen 200 S. 10th St. 1 (MCTX1) Not disclosed Former CarrierCOM
UT Austin TACC Round Rock Inside Sabey SDC Austin 1 colocated system Not disclosed Horizon, the largest NSF academic supercomputer

Power, policy, and moratoriums

“Simply put, Texans must come first. Data centers must pay their own way, protect our grid and water, and complete the ERCOT and TWDB audits.”

Governor Abbott said that on September 21, 2026, as he ordered the Texas Commission on Environmental Quality to issue no permits to data center projects until two state audits are finished, with a compliance report due October 19. It was the third step in seven weeks. On August 3 he directed the Public Utility Commission and ERCOT to verify every large-load project in the interconnection queue before approving another, and ERCOT the same day suspended approvals to energize any data center or crypto facility of 75 megawatts or more and paused its “Batch Zero” study of roughly 250 to 300 projects representing about 200 GW; ERCOT says it will file its verification report on December 10. On September 14 he told the Texas Water Development Board to prosecute data centers that ignore its water survey, after only 28 percent of them answered it. Behind the orders are the numbers: 474 GW of requests against a grid whose all-time peak, set on July 22, 2026, was 91,134 MW; a preliminary long-term forecast that shows demand quadrupling by 2032 and that ERCOT’s own chief executive called higher than he expects; and, on the other side of the ledger, only 9,042 MW of large load actually approved to connect.

The framework the governor is enforcing is Senate Bill 6, signed in June 2025: loads of 75 megawatts or more must pay a minimum $100,000 study fee, disclose duplicate requests elsewhere in Texas and any backup generation, install remote-disconnect equipment so ERCOT can shed them in an emergency, and share transmission costs. The commission’s implementing rule, still pending, would add $50,000 per megawatt of financial security. The utilities have taken the orders in stride because their queues are unmanageable anyway: Oncor reported 298 GW of large-load requests at midyear, CenterPoint says 12.2 GW of Houston load is firmly committed with 8 GW of it data centers to be energized by 2029, and CPS Energy in San Antonio counts 59 projects asking for about 26,000 MW against a system that peaks near 5,000. The $33 billion plan to build the state’s first 765-kilovolt transmission lines, justified largely by West Texas load, hit its own wall in August when the lieutenant governor asked the commission to deny every pending line certificate until the 2027 session; hearings run through October 2. Vistra, whose Comanche Peak nuclear plant will sell 1,200 MW to Amazon from 2027, told investors it would “like to see the queues culled.”

The dome of the Texas State Capitol in Austin against a clear sky, with the United States and Texas flags flying from the roof below it

Photo: Ruben Reyes / Pexels

Money and land are the other fronts. The data center sales tax exemption, which cost $14.6 million in its first biennium, is projected at $1.3 billion for fiscal 2026 and $3.3 billion for 2028 to 2029; the Comptroller has audited 20 of the 138 qualified projects and found 6 in breach, the Senate Finance Committee held a hearing on it July 27, and Abbott now says he will work to eliminate data center incentives entirely. Because Texas counties have no zoning power, the local response has run through cities and tax abatements: San Marcos banned data centers outright in June, Fort Worth voted unanimously in August for a moratorium that takes effect in February 2027 and created a data center commission, Denton is on track to adopt one in December, Forney, Lewisville, Mesquite, and El Paso wrote setback and permit ordinances, and Austin is drafting a “high-impact” land use class with a no-incentives policy. Guadalupe, Archer, and Brazoria counties each refused abatements in 2026, and Hood County’s rejection of a moratorium came after a state senator warned commissioners they had no power to impose one. Water use, per the Houston Advanced Research Center, was about 25 billion gallons in 2025 and could reach 161 billion a year by 2030; San Antonio’s Microsoft and Army Corps sites drew 463 million gallons through a Stage 3 drought, while Stargate Abilene, running dry cooling, drew 20 gallons a minute against a 500-gallon allocation.

How this list is maintained

A row appears here when a named operator, a county record, a state registration, or an industry tracker lists a campus in Texas and its location or operator can be confirmed on the operator’s own site, in a government filing, or in a news report, or when a proposal has a named locality and a published source; rows that rest on a tracker alone say so. Because Texas has hundreds of colocation buildings, that table lists one row per operator per metro; hyperscale rows are one per campus. Corrections and additions are welcome through the About page, and every refresh is marked with an updated date at the top of the page.